HEARTLAND 2 — Project Summary

Queue ID
CAISO-1380
Capacity
156.05 MW
Technology
Solar
Status
active
Location
Fresno, CA
Region
CAISO
Developer
IA Status
IA Executed

HEARTLAND 2

BetaActiveSolarCAISOLBNL + Live

156.05 MW generation in Fresno, CA · In queue since May 2017 · Proposed COD June 2028

156.05 MW

Capacity

1

Components

Solar

8y 10m

In Queue

IA Executed

IA Status

Signed Dec 2023

Interconnection Timeline

Queue → IA

6y 7m

IA → COD

4y 6m

Total Duration

6y 7m

Construction75%
Queue EntryMay 1, 2017

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementDec 4, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-06-30

Project Details

State

CA

County

Fresno

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Tranquility 230 kV

Data Source

LBNL + Live