HEARTLAND 1
BetaActiveSolarCAISOLBNL + Live
156.04 MW generation in Fresno, CA · In queue since May 2017 · Proposed COD June 2028
156.04 MW
Capacity
1
Components
Solar
8y 10m
In Queue
IA Executed
IA Status
Signed Dec 2023
Interconnection Timeline
Queue → IA
6y 7m
IA → COD
4y 6m
Total Duration
6y 7m
Construction75%
Queue EntryMay 1, 2017
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementDec 4, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-06-30
Project Details
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Tranquility 230 kV
Data Source
LBNL + Live
No news available for this project.