GONZAGA WIND FARM
BetaActiveWindCAISOLBNL + Live
80 MW generation in Merced, CA · In queue since May 2017 · Proposed COD March 2026
80 MW
Capacity
1
Components
Wind
8y 10m
In Queue
IA Executed
IA Status
Signed Oct 2019
Interconnection Timeline
Queue → IA
2y 5m
IA → COD
6y 5m
Total Duration
2y 5m
Construction75%
Queue EntryMay 1, 2017
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementOct 30, 2019
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-03-31
Project Details
State
CA
County
Merced
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Los Banos 70 kV
Data Source
LBNL + Live
No news available for this project.