ROCCASECCA BESS
BetaActiveWindBatteryCAISOLBNL + Live
405 MW hybrid in Clark, NV · In queue since May 2016 · Proposed COD March 2027
405 MW
Capacity
2
Components
Wind + Battery
9y 10m
In Queue
IA Executed
IA Status
Signed Dec 2018
Interconnection Timeline
Queue → IA
2y 7m
IA → COD
8y 3m
Total Duration
2y 7m
Construction75%
Queue EntryMay 2, 2016
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementDec 3, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–36 months
Commercial Operation
Proposed COD: 2027-03-01
Technology
Wind310 MW · 77%
Battery95 MW · 23%
Project Details
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
Sloan Canyon Switching Station 230kV
Data Source
LBNL + Live