TAHOE
300 MW storage in Clark, NV · In queue since May 2016 · Proposed COD May 2026
300 MW
Capacity
1
Components
Battery
9y 10m
In Queue
IA Executed
IA Status
Signed Jul 2018
Queue → IA
2y 2m
IA → COD
7y 10m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-05-01
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
SCE owned Eldorado Bus 230kV
Data Source
LBNL + Live
NV Energy on upcoming Lake Tahoe and Sierra electricity changes
After the news broke about the 2027 changes to how Liberty obtains its power from NV Energy, some level of panic settled in at Lake Tahoe.
Nevada likely to fall short of clean energy goals because of data centers
Six years after Nevada voters approved a constitutional amendment requiring in-state utilities to get half of their power from renewable...
Data centers, Greenlink, and your electricity bill
Overlooking the Truckee River along USA Parkway in Storey County, Nevada, across from a pair of concrete signs proclaiming “Tahoe-Reno...
Data centers, Greenlink, and your electricity bill
Overlooking the Truckee River along USA Parkway in Storey County, Nevada, across from a pair of concrete signs proclaiming “Tahoe-Reno...
Last updated 2026-03-26