PASTORIA SOLAR
BetaActiveSolarBatteryCAISOLBNL + Live
186.875 MW hybrid in Kern, CA · In queue since May 2016 · Proposed COD May 2026
186.875 MW
Capacity
2
Components
Solar + Battery
9y 10m
In Queue
IA Executed
IA Status
Signed Dec 2018
Interconnection Timeline
Queue → IA
2y 7m
IA → COD
7y 5m
Total Duration
2y 7m
Construction75%
Queue EntryMay 2, 2016
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementDec 4, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2026-05-04
Technology
Solar106.875 MW · 57%
Battery80 MW · 43%
Project Details
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Pastoria Substation 230kV
Data Source
LBNL + Live
No news available for this project.