DAGGETT SOLAR 3
521.88 MW hybrid in San Bernardino, CA · In queue since May 2016 · Proposed COD August 2023
521.88 MW
Capacity
2
Components
Solar + Battery
9y 10m
In Queue
IA Executed
IA Status
Signed Dec 2018
Queue → IA
2y 7m
IA → COD
4y 8m
Total Duration
2y 7m
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2023-08-06
State
CA
County
San Bernardino
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Kramer Substation 230kV
Data Source
LBNL + Live
Clearway Energy closes financing, begins construction on 1,280MWh Utah BESS portfolio
IPP Clearway Energy Group has closed financing and started construction on its 1,280MWh Honeycomb battery energy storage system (BESS)...
Clearway Energy closes financing, begins construction on 1,280MWh Utah BESS portfolio
IPP Clearway Energy Group has closed financing and started construction on its 1,280MWh Honeycomb battery energy storage system (BESS)...
Clearway Energy closes financing, begins construction on 1,280MWh Utah BESS portfolio
IPP Clearway Energy Group has closed financing and started construction on its 1,280MWh Honeycomb battery energy storage system (BESS)...
Clearway Energy closes financing, begins construction on 1,280MWh Utah BESS portfolio
IPP Clearway Energy Group has closed financing and started construction on its 1,280MWh Honeycomb battery energy storage system (BESS)...
Last updated 2026-03-26