MULQUEENEY RANCH WIND
BetaActiveWindCAISOLBNL + Live
114 MW generation in Alameda, CA · In queue since May 2016 · Proposed COD June 2026
114 MW
Capacity
1
Components
Wind
9y 10m
In Queue
IA Executed
IA Status
Signed Jul 2018
Interconnection Timeline
Queue → IA
2y 2m
IA → COD
7y 11m
Total Duration
2y 2m
Construction75%
Queue EntryMay 2, 2016
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJul 25, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
CA
County
Alameda
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Tesla 230 kV
Data Source
LBNL + Live