CORBY
BetaActiveBatteryCAISOLBNL + Live
313.5 MW storage in Solano, CA · In queue since May 2016 · Proposed COD June 2027
313.5 MW
Capacity
1
Components
Battery
9y 10m
In Queue
IA Executed
IA Status
Signed Jun 2021
Interconnection Timeline
Queue → IA
5y 1m
IA → COD
6 years
Total Duration
5y 1m
Construction75%
Queue EntryMay 2, 2016
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJun 9, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
CA
County
Solano
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Vaca-Dixon 230 kV
Data Source
LBNL + Live