KYAN SOLAR — Project Summary

Queue ID
CAISO-1260
Capacity
102 MW
Technology
Solar
Status
active
Location
Kern, CA
Region
CAISO
Developer
IA Status
IA Executed

KYAN SOLAR

BetaActiveSolarCAISOLBNL + Live

102 MW generation in Kern, CA · In queue since May 2016 · Proposed COD March 2027

102 MW

Capacity

1

Components

Solar

9y 10m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

10y 10m

Construction75%
Queue EntryMay 2, 2016

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-03-02

Project Details

State

CA

County

Kern

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Midway-Wheeler Ridge #2 230 kV Line

Data Source

LBNL + Live