PLUOT
BetaActiveSolarBatteryCAISOLBNL + Live
479 MW hybrid in Kings, CA · In queue since May 2016 · Proposed COD June 2026
479 MW
Capacity
2
Components
Solar + Battery
9y 10m
In Queue
IA Executed
IA Status
Signed Jan 2020
Interconnection Timeline
Queue → IA
3y 8m
IA → COD
6y 5m
Total Duration
3y 8m
Construction75%
Queue EntryMay 2, 2016
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJan 7, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2026-06-30
Technology
Solar254 MW · 53%
Battery225 MW · 47%
Project Details
State
CA
County
Kings
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Gates 230 kV
Data Source
LBNL + Live
No news available for this project.