SILVER RIDGE MOUNT SIGNAL
BetaActiveSolarBatteryCAISOLBNL + Live
750 MW hybrid in Imperial, CA · In queue since January 1970 · Proposed COD June 2027
750 MW
Capacity
2
Components
Solar + Battery
56y 2m
In Queue
IA Executed
IA Status
Signed Jan 1970
Interconnection Timeline
Queue → IA
<1 month
IA → COD
57y 5m
Total Duration
<1 month
Construction75%
Queue EntryJan 1, 1970
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJan 1, 1970
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-06-01
Technology
Solar600 MW · 80%
Battery150 MW · 20%
Project Details
State
CA
County
Imperial
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Imperial Valley Substation 230 kV
Data Source
LBNL + Live
No news available for this project.