DAYLIGHT — Project Summary

Queue ID
CAISO-1223
Capacity
610.707 MW
Technology
Solar+Battery
Status
active
Location
Kings, CA
Region
CAISO
Developer
IA Status
IA Executed

DAYLIGHT

BetaActiveSolarBatteryCAISOLBNL + Live

610.707 MW hybrid in Kings, CA · In queue since May 2016 · Proposed COD January 2028

610.707 MW

Capacity

2

Components

Solar + Battery

9y 10m

In Queue

IA Executed

IA Status

Signed Dec 2023

Interconnection Timeline

Queue → IA

7y 7m

IA → COD

4y 1m

Total Duration

7y 7m

Construction75%
Queue EntryMay 2, 2016

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementDec 18, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-01-19

Technology
Solar310.707 MW · 51%
Battery300 MW · 49%
Project Details

State

CA

County

Kings

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Mustang 230 kV

Data Source

LBNL + Live