AGUA CALIENTE SOLAR 2
BetaActiveSolarCAISOLBNL + Live
20 MW generation in Maricopa, AZ · In queue since March 2016 · Proposed COD December 2016
20 MW
Capacity
1
Components
Solar
10 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2016
Interconnection Timeline
Total Duration
9 months
Schedule
113 months past proposed COD
In Study38%
Queue EntryMar 8, 2016
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2016-12-01
Project Details
State
AZ
County
Maricopa
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Hoodoo Wash Switchyard 500 kV
Data Source
LBNL + Live