GOLDEN FIELDS SOLAR
100 MW storage in Kern, CA · In queue since April 2015 · Proposed COD December 2026
100 MW
Capacity
1
Components
Battery
10y 11m
In Queue
IA Executed
IA Status
Signed Dec 2019
Queue → IA
4y 8m
IA → COD
7 years
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-12-01
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Whirlwind Substation 230kV
Data Source
LBNL + Live
Clearway negotiates 560MWh tolling agreements with California IOU SDG&E, sells BESS to yieldco
Clearway Energy Group has negotiated tolling agreements with SDG&E for one of its solar and storage complexes in Kern County, California.
Clearway negotiates 560MWh tolling agreements with California IOU SDG&E, sells BESS to yieldco
Clearway Energy Group has negotiated tolling agreements with SDG&E for one of its solar and storage complexes in Kern County, California.
Clearway negotiates 560MWh tolling agreements with California IOU SDG&E, sells BESS to yieldco
Clearway Energy Group has negotiated tolling agreements with SDG&E for one of its solar and storage complexes in Kern County, California.
Clearway negotiates 560MWh tolling agreements with California IOU SDG&E, sells BESS to yieldco
Clearway Energy Group has negotiated tolling agreements with SDG&E for one of its solar and storage complexes in Kern County, California.
Last updated 2026-03-26