SIENNA SOLAR FARM
BetaActiveSolarBatteryCAISOLBNL + Live
400 MW hybrid in San Bernardino, CA · In queue since April 2015 · Proposed COD January 2027
400 MW
Capacity
2
Components
Solar + Battery
10y 11m
In Queue
IA Executed
IA Status
Signed Nov 2017
Interconnection Timeline
Queue → IA
2y 7m
IA → COD
9y 2m
Total Duration
2y 7m
Construction75%
Queue EntryApr 30, 2015
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementNov 7, 2017
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-01-28
Technology
Solar200 MW · 50%
Battery200 MW · 50%
Project Details
State
CA
County
San Bernardino
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Calcite Substation 230kV
Data Source
LBNL + Live
No news available for this project.