FALLBROOK ENERGY STORAGE — Project Summary

Queue ID
CAISO-1169
Capacity
69.6 MW
Technology
Battery
Status
active
Location
San Diego, CA
Region
CAISO
Developer
IA Status
IA Executed

FALLBROOK ENERGY STORAGE

BetaActiveBatteryCAISOLBNL + Live

69.6 MW storage in San Diego, CA · In queue since April 2015 · Proposed COD March 2026

69.6 MW

Capacity

1

Components

Battery

10y 11m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

10y 11m

Schedule

1 months past proposed COD

Construction75%
Queue EntryApr 30, 2015

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-03-06

Project Details

State

CA

County

San Diego

Region

CAISO

Developer

Utility

SDGE

Entity

CAISO

Point of Interconnection

Avocado Substation 69 kV

Data Source

LBNL + Live