SCARLET
800 MW hybrid in Fresno, CA · In queue since April 2015 · Proposed COD December 2025
800 MW
Capacity
2
Components
Solar + Battery
10y 11m
In Queue
IA Executed
IA Status
Signed Nov 2017
Queue → IA
2y 7m
IA → COD
8y 1m
Total Duration
2y 7m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-12-23
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Tranquility 230 kV
Data Source
LBNL + Live
Georgia Power kicks off construction on 765 MW of BESS | Projects Weekly
Georgia Power has commenced construction on 765 MW of new battery energy storage systems (BESS) strategically located across Georgia in Bibb, Lowndes, Floyd...
Georgia Power kicks off construction on 765 MW of BESS | Projects Weekly
Georgia Power has commenced construction on 765 MW of new battery energy storage systems (BESS) strategically located across Georgia in Bibb, Lowndes, Floyd...
Georgia Power kicks off construction on 765 MW of BESS | Projects Weekly
Georgia Power has commenced construction on 765 MW of new battery energy storage systems (BESS) strategically located across Georgia in Bibb, Lowndes, Floyd...
Georgia Power kicks off construction on 765 MW of BESS | Projects Weekly
Georgia Power has commenced construction on 765 MW of new battery energy storage systems (BESS) strategically located across Georgia in Bibb, Lowndes, Floyd...
Last updated 2026-03-26