LUNA VALLEY SOLAR
BetaActiveSolarBatteryCAISOLBNL + Live
372.5 MW hybrid in Fresno, CA · In queue since April 2015 · Proposed COD December 2028
372.5 MW
Capacity
2
Components
Solar + Battery
10y 11m
In Queue
IA Executed
IA Status
Signed Nov 2018
Interconnection Timeline
Queue → IA
3y 7m
IA → COD
10y 1m
Total Duration
3y 7m
Construction75%
Queue EntryApr 30, 2015
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementNov 25, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2028-12-29
Technology
Solar204 MW · 55%
Battery168.5 MW · 45%
Project Details
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Tranquility 230 kV
Data Source
LBNL + Live