LITTLE BEAR 4
103.09 MW generation in Fresno, CA · In queue since April 2015 · Proposed COD February 2029
103.09 MW
Capacity
1
Components
Solar
10y 11m
In Queue
IA Executed
IA Status
Signed Nov 2017
Queue → IA
2y 7m
IA → COD
11y 3m
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-02-02
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Mendota Substation 115kV
Data Source
LBNL + Live
Update: Bear Valley Electric rates increase March 1
Brace yourselves, Big Bear. It turns out electricity rates via Bear Valley Electric Service will increase sooner than anticipated.
Update: Bear Valley Electric rates increase March 1
Brace yourselves, Big Bear. It turns out electricity rates via Bear Valley Electric Service will increase sooner than anticipated.
Update: Bear Valley Electric rates increase March 1
Brace yourselves, Big Bear. It turns out electricity rates via Bear Valley Electric Service will increase sooner than anticipated.
Update: Bear Valley Electric rates increase March 1
Brace yourselves, Big Bear. It turns out electricity rates via Bear Valley Electric Service will increase sooner than anticipated.
Last updated 2026-03-26