LITTLE BEAR 3
20.44 MW generation in Fresno, CA · In queue since April 2015 · Proposed COD February 2029
20.44 MW
Capacity
1
Components
Solar
10y 11m
In Queue
IA Executed
IA Status
Signed Nov 2017
Queue → IA
2y 7m
IA → COD
11y 3m
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-02-02
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Mendota Substation 115kV
Data Source
LBNL + Live
Longroad signs toll PPA for hybrid solar-BESS project in California with Marin Clean Energy
Longroad Energy has secured a power purchase agreement (PPA) for one of its hybrid solar and BESS projects located in San Benito County, California.
Longroad signs toll PPA for hybrid solar-BESS project in California with Marin Clean Energy
Longroad Energy has secured a power purchase agreement (PPA) for one of its hybrid solar and BESS projects located in San Benito County, California.
Longroad signs toll PPA for hybrid solar-BESS project in California with Marin Clean Energy
Longroad Energy has secured a power purchase agreement (PPA) for one of its hybrid solar and BESS projects located in San Benito County, California.
Longroad Energy, Swinerton complete 160-MWac Little Bear solar project in California
MCE and Longroad Energy are excited to announce the completion of the 160-MWAC/215-MWDC Little Bear solar complex in Fresno County,...
Last updated 2026-03-26