ALTAMONT MIDWAY LTD
BetaActiveWindCAISOLBNL + Live
5 MW generation in Alameda, CA · In queue since April 2015 · Proposed COD April 2027
5 MW
Capacity
1
Components
Wind
10y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
12 years
Construction75%
Queue EntryApr 13, 2015
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2027-04-28
Project Details
State
CA
County
Alameda
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Altamont Midway 230 kV
Data Source
LBNL + Live
No news available for this project.