GASKELL WEST
186.62 MW hybrid in Kern, CA · In queue since April 2014 · Proposed COD December 2026
186.62 MW
Capacity
2
Components
Solar + Battery
11y 11m
In Queue
IA Executed
IA Status
Signed Apr 2019
Queue → IA
5 years
IA → COD
7y 8m
Total Duration
5 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-12-02
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Whirlwind Substation 220 kV
Data Source
LBNL + Live
Matrix signs resource adequacy capacity deal for California battery | Energy Storage News
Spain-based renewable energy platform Matrix Renewables has sealed a resource adequacy capacity contract with not-for-profit power provider Pioneer Community...
'America's largest' energy storage plant to pioneer giant 'concrete batteries' with Biden cash boost
Westinghouse Electric Company has won US government funding for a 1.2GWh pumped thermal project it is developing in Alaska that it says will be the largest...
Norton Rose Fulbright represents Matrix Renewables USA in purchase of Gaskell West Project
Norton Rose Fulbright represented Matrix Renewables in an agreement to acquire the 105 MWac solar plus 80 MWh energy storage Gaskell West 2...
Gaskell West 1 Solar Project Begins Commercial Operation in California
Southern Power has announced the commercial operation of the 20-MW Gaskell West 1 Solar Facility in Kern County, California. This project...