ESCONDIDO ENERGY CENTER 2
BetaActiveBatteryCAISOLBNL + Live
33 MW storage in San Diego, CA · In queue since April 2014 · Proposed COD June 2030
33 MW
Capacity
1
Components
Battery
11y 11m
In Queue
IA Executed
IA Status
Signed Jan 2024
Interconnection Timeline
Queue → IA
9y 9m
IA → COD
6y 5m
Total Duration
9y 9m
Construction75%
Queue EntryApr 30, 2014
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJan 3, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2030-06-01
Project Details
State
CA
County
San Diego
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Escondido Substation 69 kV
Data Source
LBNL + Live
No news available for this project.