CHULA VISTA ENERGY CENTER 2
BetaActiveBatteryCAISOLBNL + Live
50 MW storage in San Diego, CA · In queue since April 2014 · Proposed COD April 2026
50 MW
Capacity
1
Components
Battery
11y 11m
In Queue
IA Executed
IA Status
Signed Mar 2021
Interconnection Timeline
Queue → IA
6y 11m
IA → COD
5y 1m
Total Duration
6y 11m
Construction75%
Queue EntryApr 30, 2014
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementMar 2, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-04-28
Project Details
State
CA
County
San Diego
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Otay Substation 69 kV
Data Source
LBNL + Live
No news available for this project.