LITTLE BEAR SOLAR 2
BetaActiveSolarCAISOLBNL + Live
20 MW generation in Fresno, CA · In queue since April 2014 · Proposed COD February 2029
20 MW
Capacity
1
Components
Solar
11y 11m
In Queue
IA Executed
IA Status
Signed Nov 2016
Interconnection Timeline
Queue → IA
2y 7m
IA → COD
12y 3m
Total Duration
2y 7m
Construction75%
Queue EntryApr 30, 2014
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementNov 15, 2016
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2029-02-01
Project Details
State
CA
County
Fresno
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Mendota Substation 115 kV
Data Source
LBNL + Live