WINDSTAR I ALTERNATE
BetaActiveWindBatteryCAISOLBNL + Live
240 MW hybrid in Kern, CA · In queue since April 2006 · Proposed COD October 2030
240 MW
Capacity
2
Components
Wind + Battery
19y 11m
In Queue
IA Executed
IA Status
Signed Aug 2022
Interconnection Timeline
Queue → IA
16y 4m
IA → COD
8y 2m
Total Duration
16y 4m
Construction75%
Queue EntryApr 5, 2006
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementAug 5, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–36 months
Commercial Operation
Proposed COD: 2030-10-15
Technology
Wind120 MW · 50%
Battery120 MW · 50%
Project Details
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Vincent Substation 230kV
Data Source
LBNL + Live
No news available for this project.