BetaActiveSolarBPALBNL
1 MW generation in Deschutes, OR · In queue since October 2024 · Proposed COD August 2025
1 MW
Capacity
1
Components
Solar
1y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
10 months
Schedule
8 months past proposed COD
In Study38%
Queue EntryOct 25, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-08-01
Project Details
State
OR
County
Deschutes
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Central Electric Cooperative's (CEC) 12.5kV distribution line served via CEC's Knott Substation
Data Source
LBNL
No news available for this project.