20 MW generation in Harney, OR · In queue since July 2024 · Proposed COD March 2025
20 MW
Capacity
1
Components
Solar
1y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
8 months
Schedule
12 months past proposed COD
In Study38%
Queue EntryJul 23, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-03-31
Project Details
State
OR
County
Harney
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
43.439458, -118.704502 for 9.9 MW; 43.438922, -118.704502 for 9.9 MW at Harney 115kV Substation
Data Source
LBNL
No news available for this project.