BetaActiveSolarBPALBNL
1 MW generation in Clark, WA · In queue since June 2024 · Proposed COD November 2024
1 MW
Capacity
1
Components
Solar
1y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
5 months
Schedule
17 months past proposed COD
In Study38%
Queue EntryJun 21, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-07
Project Details
State
WA
County
Clark
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Sifton 115kV Substation
Data Source
LBNL
No news available for this project.