— Project Summary

Queue ID
BPA-G1064
Capacity
15 MW
Technology
Battery
Status
active
Location
Umatilla, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryBPALBNL

15 MW storage in Umatilla, OR · In queue since April 2024 · Proposed COD January 2026

15 MW

Capacity

1

Components

Battery

1y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

1y 9m

Schedule

3 months past proposed COD

In Study38%
Queue EntryApr 16, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-01

Project Details

State

OR

County

Umatilla

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

UEC Westland to McNary 230 kV line that terminates in the 230 kV Bay 16 terminal of the McNary Substation.

Data Source

LBNL

No news available for this project.