BetaActiveBatteryBPALBNL
15 MW storage in Umatilla, OR · In queue since April 2024 · Proposed COD January 2026
15 MW
Capacity
1
Components
Battery
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
1y 9m
Schedule
3 months past proposed COD
In Study38%
Queue EntryApr 16, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-01
Project Details
State
OR
County
Umatilla
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
UEC Westland to McNary 230 kV line that terminates in the 230 kV Bay 16 terminal of the McNary Substation.
Data Source
LBNL