BetaActiveSolarBatteryBPALBNL
175 MW hybrid in Umatilla, OR · In queue since January 2024 · Proposed COD December 2026
175 MW
Capacity
2
Components
Solar + Battery
2y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 11m
In Study38%
Queue EntryJan 23, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Technology
Solar110 MW · 63%
Battery65 MW · 37%
Project Details
State
OR
County
Umatilla
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Morrow Flat 230kV
Data Source
LBNL
No news available for this project.