BetaActiveBatteryBPALBNL
1,300 MW storage in Wasco, OR · In queue since November 2023 · Proposed COD December 2032
1,300 MW
Capacity
1
Components
Battery
2y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2032
Interconnection Timeline
Total Duration
9y 1m
In Study38%
Queue EntryNov 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2032-12-01
Project Details
State
OR
County
Wasco
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Maupin-Redmond No 1 230 kV line
Data Source
LBNL
No news available for this project.