BetaActiveBatteryBPALBNL
650 MW storage in Harney, OR · In queue since November 2023 · Proposed COD December 2029
650 MW
Capacity
1
Components
Battery
2y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 1m
In Study38%
Queue EntryNov 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-03
Project Details
State
OR
County
Harney
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Brasada-Harney No 1 115 kV line
Data Source
LBNL
No news available for this project.