BetaActiveWindBatteryBPALBNL
750 MW hybrid in Sherman, OR · In queue since November 2023 · Proposed COD January 2027
750 MW
Capacity
2
Components
Wind + Battery
2y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 2m
In Study38%
Queue EntryNov 21, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-01-06
Technology
Wind500 MW · 67%
Battery250 MW · 33%
Project Details
State
OR
County
Sherman
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Ashe-Marion No 2 500 kV line.
Data Source
LBNL
No news available for this project.