— Project Summary

Queue ID
BPA-G1041
Capacity
750 MW
Technology
Wind+Battery
Status
active
Location
Sherman, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBatteryBPALBNL

750 MW hybrid in Sherman, OR · In queue since November 2023 · Proposed COD January 2027

750 MW

Capacity

2

Components

Wind + Battery

2y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 2m

In Study38%
Queue EntryNov 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-06

Technology
Wind500 MW · 67%
Battery250 MW · 33%
Project Details

State

OR

County

Sherman

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Ashe-Marion No 2 500 kV line.

Data Source

LBNL

No news available for this project.