— Project Summary

Queue ID
BPA-G1036
Capacity
234 MW
Technology
Wind
Status
active
Location
Hood River, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBPALBNL

234 MW generation in Hood River, OR · In queue since November 2023 · Proposed COD October 2028

234 MW

Capacity

1

Components

Wind

2y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 11m

In Study38%
Queue EntryNov 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-31

Project Details

State

OR

County

Hood River

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Big Eddy-Troutdale No 1 230 kV line

Data Source

LBNL

No news available for this project.