— Project Summary

Queue ID
BPA-G1027
Capacity
260 MW
Technology
Solar
Status
active
Location
Umatilla, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

260 MW generation in Umatilla, OR · In queue since November 2023 · Proposed COD December 2028

260 MW

Capacity

1

Components

Solar

2y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 1m

In Study38%
Queue EntryNov 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

OR

County

Umatilla

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Stanfield Substation at 230 kV

Data Source

LBNL

No news available for this project.