BetaActiveSolarWindBatteryBPALBNL
1,554 MW hybrid in Douglas, WA · In queue since November 2023 · Proposed COD December 2029
1,554 MW
Capacity
3
Components
Solar + Wind + Battery
2y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 1m
In Study38%
Queue EntryNov 21, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-01
Technology
Solar508.5 MW · 33%
Wind530.4 MW · 34%
Battery515.1 MW · 33%
Project Details
State
WA
County
Douglas
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Columbia Substation
Data Source
LBNL
No news available for this project.