BetaActiveWindBPALBNL
250.1 MW generation in Umatilla, OR · In queue since November 2023 · Proposed COD December 2030
250.1 MW
Capacity
1
Components
Wind
2y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 1m
In Study38%
Queue EntryNov 21, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-12-31
Project Details
State
OR
County
Umatilla
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Combine Hills II tap to Walla Walla-Pendleton No 1 69 kV line
Data Source
LBNL
No news available for this project.