BetaActiveSolarBPALBNL
3 MW generation in Adams, WA · In queue since November 2023 · Proposed COD December 2025
3 MW
Capacity
1
Components
Solar
2y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 1m
Schedule
3 months past proposed COD
In Study38%
Queue EntryNov 16, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
WA
County
Adams
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Hatton tap to Connell tap to Benton-Scooteney No 1 115kV line
Data Source
LBNL