BetaActiveNuclearBPALBNL
1,120 MW generation in Benton, WA · In queue since November 2023 · Proposed COD December 2030
1,120 MW
Capacity
1
Components
Nuclear
2y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 1m
In Study38%
Queue EntryNov 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-12-31
Project Details
State
WA
County
Benton
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Ashe Substation at 230kV and 500 kV
Data Source
LBNL
No news available for this project.