BetaActiveSolarBatteryBPALBNL
500 MW hybrid in Sherman, OR · In queue since October 2023 · Proposed COD January 2026
500 MW
Capacity
2
Components
Solar + Battery
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 3m
Schedule
3 months past proposed COD
In Study38%
Queue EntryOct 27, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-02
Technology
Solar250 MW · 50%
Battery250 MW · 50%
Project Details
State
OR
County
Sherman
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Biglow Canyon _x0013_ John Day No 1 230 kV line
Data Source
LBNL