BetaActiveWindBPALBNL
19 MW generation in Umatilla, OR · In queue since October 2023 · Proposed COD December 2023
19 MW
Capacity
1
Components
Wind
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2 months
Schedule
28 months past proposed COD
In Study38%
Queue EntryOct 16, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
OR
County
Umatilla
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Walla Walla-Pendleton 69kV line
Data Source
LBNL