— Project Summary

Queue ID
BPA-G0974
Capacity
250 MW
Technology
Wind
Status
active
Location
Wasco, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBPALBNL

250 MW generation in Wasco, OR · In queue since October 2023 · Proposed COD December 2029

250 MW

Capacity

1

Components

Wind

2y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

6y 2m

In Study38%
Queue EntryOct 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-01

Project Details

State

OR

County

Wasco

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Parkdale Substation

Data Source

LBNL