10 MW generation in Benton, WA · In queue since October 2023 · Proposed COD July 2027
10 MW
Capacity
1
Components
Solar
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 9m
In Study38%
Queue EntryOct 6, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
WA
County
Benton
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Benton-White Bluffs No 1 line or White Bluffs-Richland No 1 line
Data Source
LBNL
No news available for this project.