— Project Summary

Queue ID
BPA-G0955
Capacity
350 MW
Technology
Wind
Status
active
Location
Lincoln, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBPALBNL

350 MW generation in Lincoln, WA · In queue since October 2023 · Proposed COD September 2026

350 MW

Capacity

1

Components

Wind

2y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 11m

In Study38%
Queue EntryOct 6, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-01

Project Details

State

WA

County

Lincoln

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

TBD

Data Source

LBNL

No news available for this project.