— Project Summary

Queue ID
BPA-G0952
Capacity
650 MW
Technology
Battery
Status
active
Location
Gilliam, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryBPALBNL

650 MW storage in Gilliam, OR · In queue since October 2023 · Proposed COD June 2029

650 MW

Capacity

1

Components

Battery

2y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 8m

In Study38%
Queue EntryOct 5, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-06-01

Project Details

State

OR

County

Gilliam

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

John Day Substation at 500 kV

Data Source

LBNL