— Project Summary

Queue ID
BPA-G0945
Capacity
202 MW
Technology
Solar+Battery
Status
active
Location
Fremont, ID
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryBPALBNL

202 MW hybrid in Fremont, ID · In queue since October 2023 · Proposed COD June 2026

202 MW

Capacity

2

Components

Solar + Battery

2y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 8m

In Study38%
Queue EntryOct 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-01

Technology
Solar150 MW · 74%
Battery52 MW · 26%
Project Details

State

ID

County

Fremont

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Goshen-Drummond No 1 161kV line

Data Source

LBNL

No news available for this project.