BetaActiveSolarBatteryBPALBNL
202 MW hybrid in Fremont, ID · In queue since October 2023 · Proposed COD June 2026
202 MW
Capacity
2
Components
Solar + Battery
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 8m
In Study38%
Queue EntryOct 4, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-01
Technology
Solar150 MW · 74%
Battery52 MW · 26%
Project Details
State
ID
County
Fremont
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Goshen-Drummond No 1 161kV line
Data Source
LBNL
No news available for this project.