261 MW generation in Morrow, OR · In queue since October 2023 · Proposed COD September 2026
261 MW
Capacity
1
Components
Solar
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 11m
In Study38%
Queue EntryOct 3, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
OR
County
Morrow
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Six Mile Substation; Secondary: Boardman-Alkali No 1 115kV line
Data Source
LBNL