— Project Summary

Queue ID
BPA-G0938
Capacity
300 MW
Technology
Battery
Status
active
Location
Benton, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryBPALBNL

300 MW storage in Benton, WA · In queue since September 2023 · Proposed COD January 2027

300 MW

Capacity

1

Components

Battery

2y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 4m

In Study38%
Queue EntrySep 22, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-06

Project Details

State

WA

County

Benton

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Webber Canyon Substation

Data Source

LBNL